Case Study
An Early Learning Center and Elementary School is a new 152,000 square foot two story building. It consists of K-5 classroom spaces, dining area, gymnasium and media center. The building is structural steel framed with slab on grade and concrete slab on composite steel deck.
Challenge
The project is a four prime contractor job.
General Construction
Electrical Construction
HVAC Construction
Plumbing Construction
MYCO was awarded the Plumbing Construction contract.
solution
Underground and above ground is PVC pipe and the installation was assisted by the GPS total station system. The domestic water system was completed using Pro-Press and Sweat combined. The school will have 2lb gas for the natural gas system. It is piped using black iron welded or screwed. All fixtures have low water consumption for LEED Silver rating.
Successful Outcome
The success of the project will be weighed in the coming months, but, all signs point in that direction.